Hye,
 
At relaince jamnagar's SRU (Sulfur Recovery Unit), we r facing severe blistering problems at top half (above catalyst bed) of claus bed adsorption (CBA) reactors.
 
The metallurgy is SA516 Gr-70 + 250-300 microns of aluminisation. The operating tempetature is cyclic in nature due to inherent characteristics of CBA cycle. It varies from 150 deg C & 340 deg C. The aliminisation coating gets peeled off especially near top half inlet nozzles & manways. Also at long seams & circ seams at top half, the coating gets peeled off and further corrosion on exposed based metal takes place.
 
Plz share similar experiences and solutions to avoid these problems..
 
Regards,
Jitesh 


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...