Wednesday, September 16, 2009

[MW:3224] Re: Two WPS for same Material and job

hallo dear wqar,
wps means welding process specification.
wps is submitted for the process specification for first time only if the affecting perameters are not going to be changed.
as far as i concern you jast have to qualified the welder for the same procces.

--- On Wed, 9/16/09, waqas suleman <waqas.suleman@gmail.com> wrote:

From: waqas suleman <waqas.suleman@gmail.com>
Subject: [MW:3221] Two WPS for same Material and job
To: materials-welding@googlegroups.com
Date: Wednesday, September 16, 2009, 12:49 AM

I have one query regarding the submition of WPS to client.In the starting of project i submitted a WPS for SMAW and GTAW for our project job.
Now i hired some welder from other company,but their certificate is certified on different WPS no.
Can i submit two WPS for the same job?bcause our PID inspecter rejected them for the approval of JCC card.
Please give me some refernce of code so i can convince them that they are applicable for this job.
 
 
Regards,
Waqas


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

Re: [MW:34832] Inquiry about Single Bevel with Back Grinding

Dear Uday, As per your question that one is called with backing only,Simple both side you are welding it is backing with strip or without st...