[MW:2208] Re: Socket Welding

not required if u have approved or qualified wps/pqr in the same material as per ASME SEC IX.
 
refer sec ix article 4
 
Kevin mathew


From: BR <raghurambathula@gmail.com>
To: Materials & Welding <materials-welding@googlegroups.com>
Sent: Monday, 18 May, 2009 7:49:06 PM
Subject: [MW:2207] Re: Socket Welding


Is it a procedure qualification or performance qualification? what is
your code of construction?

You can use groove weld qualification PQR/WQT for socket welds too,
else you may qaulify on a fillet weld test plate depending on your
requirement (2F,3F, 5F etc.)

however in general most the client/PMC doesn't allow fillet weld
qualified welders on any pressure welds. no restriction in code

On May 18, 6:03 pm, babu k <kbabu...@gmail.com> wrote:
> Hi,
>
> Is there any requirement for qualification of Socket welding?
>
> Thanks & regards,
>
> K.Babu
> Singapore

Bollywood news, movie reviews, film trailers and more! Click here.
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...