Purpose of Pre heating are as follows:
1) To prevent Hydrogen Induced cracking- This risk is very high with CS material if thickness is more than 25 mm thick.
2) TO remove moisture and minor dust and dirt
3) It reduces fast cooling otheriwse it results in to unwanted unhealthy mircrostructure.
4) It some time help for distortion control.
Regards
On Thu, May 7, 2009 at 11:20 AM, nilesh <nilesh_parsekar@yahoo.com> wrote:
Dear Saul,We are also tank fabricator but we never do preheating.It is not the requirement as per API 650 if you have proper WPS with supporting PQR.We have welded 35mm A 516 GR 70 in our last project without preheating without anyproblem.regdsNilesh Parsekar,Sr QC Co-ordinator(Dip Mech,API 510,API 570,AWS-CWI,NDT LEVEL2)Belleli Energy SpaFUJAIRAH - UAE
--- On Wed, 5/6/09, SAUL VASQUEZ T. <svasquez@ingetanques.com> wrote:
From: SAUL VASQUEZ T. <svasquez@ingetanques.com>
Subject: [MW:2114] preheat SA- 516 gr 70
To: materials-welding@googlegroups.com
Date: Wednesday, May 6, 2009, 7:50 PM
Dear all
We are API 650 steel tanks with steel ASTM 516 gr70 and our client requests that preheat to 70°C - 100°C is this correct? The API 650 code section 7-1 that says that preheat at 10°C
thanks all
Cordial saludo
Kind regards
Saul Vasquez T.
--------------------------------
INGETANQUES LTDA
Cra 8B Nº 190-81
Tel. 57 (1) 6794382 Fax 57 (1) 6723793
CEL. 320-3469363 y 316-5388051
Bogota D.C. Colombia. http://www.ingetanques.com/
P Antes de imprimir este mensaje, asegúrese que es necesario. El medio
ambiente está en nuestras manos. No malgastes los recursos. Ten en cuenta
que son limitados.
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---
Comments