[MW:1742] Re: 1733] ASME Sec VIII Div 1 vessel nozzle repair

Raj,
This query is from Yemen. You can also inform that the repair can be carried out only by a R stamp holder authorised by NBIC.
Any repair especially when it is U stamped.

 
On 3/9/09, Raj <nrajasek@eim.ae> wrote:

Any repair or alteration requires AI involvement and shall be done by 'R' cert holder meeting requirements of NBIC nb23

Rgds

N.Rajasekaran

AI-Dubai

00971-50-4441619

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of G Padmanabhan
Sent: Friday, March 06, 2009 10:38 PM
To: materials-welding@googlegroups.com
Subject: [MW:1733] ASME Sec VIII Div 1 vessel nozzle repair

 

Dear all,
In our project we have received " U"  stamp vessel from Europe.Manufacturer forget to take some nozzle joints radiography as per project requirements.They informed site to take radiorgphy.We found that one nozzle first circumferential  joint  repair in radiography.For this repair any AI inspection required or not?

Whether site can do this repair & required ndt.

Throw some light on this matter.

--
With Warm regards,

G.Padmanabhan
00967771103169


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...