[MW:1724] Re: Please reply this mail

Dear Mr.Jivan,
Pneumatic testing of reinforcing pad is npt mandatory . But you need to see the purpose being served by the pad. If it is a pad to attach a structural part where no through opening is made, it is not required. However if there is a through opening and  such opening is being reinforced with a pad, you need to examine the weld integrity between the pad and the branching nozzle . Therefore it is a standrd practice to do pneumatic test of such pad and  you will be able to see the weld at Pad to Nozzle , Pad to mother pipe / veseel which is typically a fillet weld and  if  accessible , you also can see the weld of  branch nozzle to main pipe/ vessel examining at inside .
I beleive that underlying inetent of test is realised now.
WithBest Regards,
Tagore

On Sat, Mar 7, 2009 at 5:02 AM, <jivanadhamane@yahoo.co.in> wrote:
 

Dear Friends/Sir,

 

Mr. Bathula Raghuram, Rajeev Arora, Mukesh Kumar, Nilesh Patahre, Joshi, Muhhemad Ibrahim, Babu K

 

First of all sorry to disturb u, as i have seen you have sent answer of lot of queries from you people for that once again i am requesting u to reply the below queries. If my question is not correct then let me know means i will correct it.

 

 

Dear Friends (Dated :- 18/02/2009)

I would like to know whether Pneumatic Test of Reinforcement Pad for branch
connection of Process Piping is mandatory as per ASME B31.3. I searhed but I
could not found any paragraph in ASME B31.3.

Regards

Jivan Dhamane

 

 

Dear Friends ( Dated :- 03/03/2009)

 

I would like to know the maximum acceptable Dry Film Thickness of the paint in % or micron for a given DFT. As per my previous experience (where I worked) as per specification that was plus/minus 30% of the total paint DFT was accptable. But I couldn't found any code or standard documents related to the maximum acceptable dry film thickness of the paint.

 

If you have any code or standard then let me know the same means i can refer same. i need this information for piping job as well as tank job.

 

Regards

 

Jivan Dhamane 



Add more friends to your messenger and enjoy! Invite them now.


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...