[MW:1521] Re: Significance of HOT PASS

Pre-heating is not as such required, but it is a good practice to use flame heating at the joint to remove the moisture or any foreign particles before starting the welding on the next day.

Regards
Sukamal Naskar
Welding Engineer 

On Mon, Feb 9, 2009 at 1:16 AM, rafique naik <rafiquenaik@hotmail.com> wrote:
Please let me know for A 106 B 16'' dia  12.7 mm thik pipe to pipe butt joint, if after root pass joint is left as it is for overnight and next morning welder wants to continue with hot pass, can he do welding  without any pre heating..
 
Regards
 
Rafique


Need more space to upload pictures? Get 25 GB online storage with Windows Live SkyDrive! Try it!




--
Sukamal Naskar
Malaysia

--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...